Skip to content
BidWriter Pro
Product ▾
How it worksFeaturesSample proposalTry it without signing upPricing
Resources ▾
Guides
What to include in an estimateHow to follow up on an estimateHow much deposit to ask forHow much does Jobber cost?Best estimating apps, with pricesAll 23 guides
Compare
vs Jobbervs Housecall Provs JoistJobber vs Housecall ProJobber vs JoistHousecall Pro vs Joist
Free
Sample estimates, 84 jobsEstimate templates, 24 tradesHourly rate calculatorMarkup vs margin calculatorJob price calculatorDeposit calculator
Company
AboutHelp centerSecurityFor customers
PricingSample
Sign inStart free
Product
How it worksFeaturesSample proposalTry it without signing upPricing
Guides
What to include in an estimateHow to follow up on an estimateHow much deposit to ask forHow much does Jobber cost?Best estimating apps, with pricesAll 23 guides
Compare
vs Jobbervs Housecall Provs JoistJobber vs Housecall ProJobber vs JoistHousecall Pro vs Joist
Free
Sample estimates, 84 jobsEstimate templates, 24 tradesHourly rate calculatorMarkup vs margin calculatorJob price calculatorDeposit calculator
Company
AboutHelp centerSecurityFor customers
Account
Sign inStart free
Last updated October 12, 2026

How to write a change order that gets accepted the same day

Home / Guides

Four lines, sent from the job site, accepted before you pick the tool back up. That is the whole system.

You opened the wall and found the thing nobody could have seen. The customer is standing there. The right move is not to explain it and keep going. It is to write four lines and get a yes before the next cut.

The four lines

  • What changed: "Found corroded galvanized supply line behind the wall, needs replacing to the main."
  • Why: "Cannot connect the new heater to it. It will leak within the year."
  • What it costs and what it does to the schedule: "Add $650. Adds half a day."
  • The okay: the customer's name and the date, typed on their phone or signed on paper.

That is a change order. It does not need a form number or a paragraph of terms. It needs those four things, written down, and agreed to before the extra work starts.

When to write one

Any time the scope, the price, or the schedule moves from what the customer accepted. A $200 change is worth two minutes. The ones that end up in a dispute are almost always the small ones that were "just mentioned" and never written down, three of them in a row, adding up to a bill the customer did not expect.

Send it the same way you sent the estimate

If the estimate was a link they accepted on their phone, the change order should be too. Same page, same accept button, same record. If you are standing next to them, show it on your phone and let them accept it there. A change order that goes out by email that night, after the work is already done, is a request for forgiveness instead of permission.

The mistake that costs the most

Doing the extra work first because it was obviously needed, then adding it to the final invoice. The customer agrees it was needed and still feels ambushed by the number. That feeling is where bad reviews come from. The fix costs you two minutes on the job site.

Keep the original estimate untouched

Do not edit the accepted estimate to a new total. Add the change order as its own line so the invoice reads: original price, change order one, change order two, deposit paid, balance due. The customer can follow it, and so can you in six months.

The same four lines work on paper, in a text, or as a short proposal of its own. If you use BidWriter Pro, write the change as a new proposal to the same customer, with the original estimate number in the first line, and send it the same way. Sending it by text is the fastest.

Free, no account: job price calculator, markup vs margin, hourly rate, and 84 sample estimates.

All guides · How to follow up on an estimate without being pushy · Why customers don't respond to your estimates · When a customer asks for a discount · How to ask a customer for a review without it feeling like a form letter · How much does Jobber cost in 2026? · How to write a bid that gets signed · How much deposit should a contractor ask for? · Estimate vs quote vs proposal: which one should you send? · How much does Housecall Pro cost in 2026? · How much does Joist cost in 2026? · What to include in a contractor estimate · How to send an estimate by text message · Estimate vs invoice: what to send and when · How to price a job: a method you can do on your phone · Good, better, best: how to put options on an estimate · Should you charge for estimates? · How to write the warranty line on an estimate · How to get paid faster as a contractor · How to write a scope of work that stops arguments · How to write an estimate on your phone, in the driveway · Eight estimate mistakes that lose jobs · The best estimating apps for small contractors, with what they cost

BidWriter Pro

Professional proposals for contractors who write their own bids. Describe the job, send it, get it signed.

Product

How it worksFeaturesPricingSample proposalHelpSecurityGuidesFree templatesSample estimatesFree toolsvs Jobbervs Housecall Provs JoistJobber alternativesBest estimating appsAbout

By trade

PlumbingElectricalRoofingHVACPaintingLandscapingFlooringConcrete / MasonryCarpentryFencingHandyman / RemodelGeneral Contractor

More trades

DrywallTileGuttersPressure WashingTree ServiceGarage DoorsSepticPest ControlSolarWindows and DoorsSidingDecks

Account

Sign inStart freesupport@getbidwriterpro.com
© 2026 BidWriter Pro LLC · 5900 Balcones Drive, Suite 27439, Austin, TX 78731 · Terms · PrivacyElectronic signatures are legally binding under the U.S. E-SIGN Act.